An old rail bed known locally as the Peanut Line carries a sewer pipe. On the Clarence side of the line, the pipe is 24 inches wide. In Amherst it narrows to 18 inches, then widens to 30 inches on the way to the treatment plant, according to Joseph Fiegl, deputy commissioner of the Erie County Division of Sewerage Management, in an interview with the Clarence Bee.
That 18-inch stretch sits outside Clarence, and it sets the pace of new housing along Clarence's busiest commercial corridor. Projects on Transit Road drain into Erie County Sewer District No. 5, which flows into Amherst's system. Clarence controls zoning on its side of the road, the county runs the sewers, and Amherst owns the line and the plant. For anyone comparing Clarence with neighboring suburbs, it explains why the apartments and townhomes already approved on Transit are arriving in pieces.
Approvals Arrive in Halves
Clarence has a name for this. Jon Bleuer, the town's Director of Community Development, told the Clarence Bee that several projects have received "phased approvals" over the years. Those approvals keep developers from finishing parts of a project until enough sewer capacity exists.
The Clarence Bee's coverage of the PB Investors approval and the Bevilacqua first phase shows how this works on two mixed-use projects on Transit Road:
| Project | What the town approved | What waits on sewer capacity |
|---|---|---|
| PB Investors / Paul Bliss, 5695 and 5731 Transit Road | Phase one of an 84-apartment plan, including a three-story, 60-unit mixed-use building | Six four-unit buildings, 24 apartments in total, held for phase two |
| Bevilacqua Development, 6625 Transit Road near Miles Road | Phase one with 31 apartments and four commercial outparcels, plus concept approval for the rest of the plan | Phase three, including the Miles Road connection |
The full Bevilacqua concept is larger than its first phase. It includes 62 apartments in two mixed-use buildings, a 28-unit apartment building, nine four-unit townhome buildings, 12 single-family lots and a quadplex. One of the Planning Board's conditions limits site disturbance to what the available sewer capacity can support.
So a buyer driving past an approved site on Transit can't tell from the road how much of the plan can be built today. The sewer schedule decides that.
Why the Town Center Starts With Restaurants and Gyms
The same limit decides the order of construction at the Eastern Hills Mall site. Uniland Development and mall owner Mountain Development plan to turn the roughly 100-acre property into a walkable town center. The town has already rezoned the site. Buffalo News coverage puts the plan at up to 1,500 residential units.
That housing comes last. In an August update to WKBW, the developers said the first phase would focus on uses that need less sewer capacity: retail, restaurants, fitness centers, medical offices, entertainment and office space. Multifamily housing and hotels, which need more capacity, are planned for later phases as the infrastructure grows. The developers also said the timing of the first construction announcements depends on the progress of sewer design and construction.
The reason goes back to the mall's original design. Fiegl explained it to the Clarence Bee:
"The infrastructure to service that site was designed for a shopping mall. It has a certain amount of flow that comes through it, and that's what it was designed for in the '70s."
He added that the redevelopment would create peak flows well above what the site carries now. He also said the plan has already been revised to add more residential units. In other words, the housing the region most wants from the site is also the use that needs the most sewer capacity.
67 Permits in a Year That Looks Busy
Market preferences have shifted toward the kind of housing that needs the most capacity. According to the Clarence Bee, single-family development was strong a decade ago, and denser multifamily buildings are more common now. That change has pushed the county and the towns to reassess downstream capacity in Sewer District No. 5 and in Amherst.
At the October 28 Town Board meeting, Councilman DiCostanzo reported 67 single-family building permits through September. He said he doubted the year would reach 100, which would keep Clarence below its recent averages. In his words, "It seems like a lot of houses are going up but it is only 67 for the year." The meeting minutes are public.
Single-family subdivisions are still moving through review. The Clarence Bee reported that SGC Development's proposed 62-home Strickler–Greiner subdivision, on about 81.5 acres, received concept-plan approval from the Planning Board. The plan sets aside 45% of the land as natural open space. A concept approval is an early step, though, and a 62-home plan spread across a site that size adds homes slowly. The denser projects along Transit, which could add homes faster, are the ones held in phases.
The Fix, in the Order It Has to Happen
The plan to remove the bottleneck has been in the Amherst/Clarence sewer agreement for well over 25 years, according to Clarence Town Engineer Tim Lavocat. Here is the sequence as it stands:
- Environmental review. On June 11, the Clarence Town Board voted to begin review of the parallel Peanut Line sewer under the State Environmental Quality Review Act, as the Clarence Bee reported. Lavocat said the project supports Clarence Master Sewer Plan 2030.
- Amherst's design and bid. The pipe runs through Amherst and belongs to Amherst, so Amherst designs and bids the project, Fiegl told the Clarence Bee. New York State Department of Environmental Conservation approvals are also required.
- Funding. In February 2026, New York State approved a $30 million grant for a new sewer line and pumping station serving the mall site and other Transit Road properties. Erie County had already committed $3 million for design and engineering, and Amherst and Clarence agreed to put in $1.6 million combined, as reported by the Buffalo News.
- Design. By August, the developers said the sewer capacity study was finished and design work was underway under Erie County's engineering team.
- Construction. Supervisor Patrick Casilio told the Buffalo News he expects construction on the improvements to likely begin in 2027. That work could overlap with a separate $6 million connector line to Transit Road that Amherst and Clarence plan to build for existing capacity needs.
Erie County's Transit Corridor sewer evaluation, revised in July 2024, shows the dependencies. The report recommends a new 24-inch parallel sewer from Transit Road to Paradise Road, which it estimated in 2023 at $3,818,195. Its preliminary schedule requires that parallel sewer to be running before the Eastern Hills pump station and force main start up, and it places that startup in years nine and ten of the program. The report also says full buildout of the area would require more capacity in the existing 30-inch sewer below Paradise Road.
What This Means When You Shop Clarence Now
For the wider market, the most recent county figures are the New York State Association of Realtors report for September 2026. In Erie County that month, 744 homes closed, down 0.7% from a year earlier, at a median price of $321,501, up 5.4%. Inventory rose 25.4% to 1,461 homes, which works out to 2.3 months of supply. These are countywide numbers. They show more listings to choose from across the region, while prices are still rising.
In Clarence, many of the new homes that would add to that supply are tied to the sewer timeline. That leads to three practical points.
The new-construction pipeline on Transit Road comes in steps. If you're waiting for new apartments or townhomes along the corridor, the phase one buildings are what's approved now. The phase two buildings and the Eastern Hills housing depend on construction that the town supervisor expects to start in 2027 at the earliest.
An empty parcel near a project may already be assigned to a later phase. Approved concept plans like Bevilacqua's show what the town expects to fill in, and the Clarence Bee covers those Planning Board actions as they happen. If you're buying near Transit, it's worth knowing what has already been approved next door.
Not every Clarence home is on public sewer. The county evaluation lists Harris Hill as an area served by private residential septic systems. It also names small treatment systems at Spaulding Lake and Clarence Research Park alongside the public sewer districts. Clarence has discussed expanding Sewer District 9 to cover parts of Harris Hill, Main Street, Sheridan Drive and Goodrich Road, according to the Amherst Bee. Fiegl has said the parallel Peanut Line would also make room for future needs such as sewers on Harris Hill. Whether a house connects to public sewer or a septic system shapes its upkeep and inspection, so confirm it for every address on your list.
FAQ
Does the sewer limit affect single-family homes on public sewer today? The phased approvals in the reporting apply to larger projects along Transit Road whose added sewer flow exceeds current capacity. An existing home already connected to public sewer is a different case from a new development that needs added capacity.
When will the Eastern Hills housing be built? The developers have not set a construction start. They say their first announcements depend on the sewer schedule, and the redevelopment will happen in phases over many years.
Who decides when the bottleneck is fixed? Three governments share the decision. Clarence handles zoning on its side of Transit Road, Erie County runs Sewer District No. 5, and the Town of Amherst designs and bids the parallel line.
If you're weighing a home near Transit Road or anywhere in Clarence, I can help you find out which approvals have been granted around a property and whether the home is on public sewer before you make an offer. Karen Baker follows these Planning Board and Town Board decisions closely. Schedule a free consultation and we'll go through the Clarence addresses on your list together.